CONSTRUCTION OF THE MAKARAC WATER SUPPLY SYSTEM – A SEPARATE PART OF THE MILNE SETTLEMENT
After a break during Christmas and New Year, the contractor Berica doo has continued the construction of the water supply system for Makarac, which is a separate part of the Milne settlement, which currently has approximately 60 residential buildings. The works began in May 2020 with a completion date of 12 months, i.e. May 2021. The dynamics of the works are on time, so it is expected that all works will be completed within the agreed deadline, i.e. before the start of the 2021 tourist season.
Some basic information about the project:
PROJECT
Water supply of the separate construction area of the settlement of Milne to the Makarac bay (joint project of the Municipality of Milna and Vodovod Brac doo)
PROJECT DOCUMENTATION
The preparation of project documentation began in 2013, the building permit was issued on 11.2.2019.
DOCUMENTATION COSTS | 150,000.00 HRK
ESTIMATED PROJECT VALUE | HRK 3,750,000.00
CONTRACTED VALUE OF WORKS | 3,345,250.38 HRK
CONTRACTOR | BERICA doo, Nerežišća
DESCRIPTION
The project includes the construction of a water supply pipeline with a length of 2650 meters and a gravity sewage collector on the initial part of the route in the settlement of Milna with a length of 275 meters from the area of Pantera to the local cemetery with a connection for the future collector system of the second separated settlement of Osibova. The pipeline is laid in existing ungraded roads with asphalt or macadam cover.